Adjustment (configuration) of relay protection devices (RPA)

Relay protection devices

Currently, the term “relay” refers to a wide group of automatic instruments and devices used in relay protection, automation, telemechanics, telephony and other branches of technology. At the end of the 19th century, the first fuses appeared, which were then replaced by electromechanical and static (analog) relay protection. In our country, since the early 1990s, such devices have been gradually replaced by digital ones. At the moment, most of the relay protection devices in Russia still belong to technology of previous generations, but at new facilities or after reconstruction in the vast majority of cases only digital relay protection is installed.

High-quality digital relay protection devices are produced by both domestic manufacturers and foreign companies. Several Russian-made devices can be noted:

  • microprocessor relay protection unit “BMRZ” (“Mekhanotronika”, St. Petersburg);
  • "SHE" (Ekra, Cheboksary);
  • "Sirius" ("Radius" Zelenograd).

Foreign-made relay protection devices:

  • "Silirotec" ("Siemens");
  • "Seliam" (Schneider Electric);
  • "SliAC", "REF" ("ABB").

Proper adjustment of relay protection also requires appropriate equipment, such as domestic RETOM-11, RETOM-21, RETOM-51, RETOM-61, or foreign analogues. It is important that the installation of relay protection is carried out only by qualified specialists who have experience and are able to perform this serious task efficiently and on time.

Causes and consequences of relay protection and automation faults

Standardized values ​​and frequency of checks, requirements for relay protection, basic methods for setting up relay protection, calculation examples are listed and described in regulatory documents: RD “Instructions for testing relay protection devices”, PTEEP , PUE 7th ed. Chapter 1.8., methodological manuals, reference books on relay protection devices. They determine that before an electrical installation is allowed to operate, it is necessary to carry out commissioning work, and for equipment up to 1000V, acceptance tests are required. Short circuits, insulation damage and overloads occur due to a number of reasons, some of which cannot be predicted - these are the actions of personnel, breakdown or peeling of insulation, wire breakage due to natural phenomena or anthropogenic influences, turning on of grounded equipment under voltage, and so on. In order to minimize the consequences of such situations, it is necessary to adjust the relay protection after installation and check the relay protection in operation.

In order to understand the principle of setting up relay protection, you need to know what happens during a short circuit. Typically, large currents of tens of thousands of amperes are applied to the fault location within a very short time. They cause not only breakdown, but also severe heating and overheating of live parts. In this case, the insulation may catch fire and the electrical installation may catch fire. Setting up relay protection allows you to automatically turn off part of the power system in order to de-energize a part of an electrical installation or a section of the network damaged as a result of an emergency. Correctly configured relay protection by timely operation reduces the consequences of an accident, as well as voltage drop in the rest of the network, stopping of electric motors and generators connected in parallel, and damage to process equipment.

0.4 kV circuit breakers also belong to relay protection; during acceptance tests, their characteristics for overload (with a time delay) and cutoff (instantaneously or with a minimum time delay) are checked. Triggering of protection devices up to 0.4 kV allows you to quickly disconnect the damaged section of the network and prevent an accident without the participation of personnel: at the moment the current supply is stopped, the electric arc goes out and the rest of the power network operates normally. This, in turn, prevents malfunctions of the main equipment, its damage and production stoppages. With proper adjustment of relay protection, enterprise losses are minimized.

Short circuits are the most common problems in power systems because they have many different causes. Also, when setting up relay protection, it is necessary to take into account that the following situations are possible:

  • phase ground fault in a network with an isolated neutral;
  • overload;
  • lowering the oil level in the transformer expander;
  • the release of gas as a result of the decomposition of oil in the transformer, and so on.

According to the requirements of PTEEP: “ power equipment of power plants , substations and electrical networks must be protected from short circuits and violations of normal operating modes by automation devices and electrical automation . Relay protection devices must be constantly turned on, except for devices that must be taken out of operation in accordance with the purpose and principle of operation, the operating mode of the power system and selectivity conditions. Emergency and warning devices must always be ready for action.” Thus, we can conclude that the second purpose of the relay protection system is to detect violations of the operating mode of electrical equipment and signal this to personnel located at a distance - in cases where personnel are present, shutdown using established relay protection is also carried out, but with a time delay, which makes it possible to use the human factor.

Configuring a LAN and a unified time system

We have combined the LAN and COEB configuration procedures into one section because this project used some switches as PTP grandmaster clocks. It was also necessary to configure the switches in terms of the PTP protocol. There were no special features in configuring COEB compared to decentralized architectures using the Sampled Values ​​protocol. However, the configuration of Ethernet switches had certain specifics. First of all, the number of Sampled Values ​​streams (for example, in project No. 2 there were 192 of them) required certain measures, since a 100 Mbit/s network is not capable of transmitting such a volume of data. Moreover, if this traffic is not filtered and is redirected by the switch to the end device (relay protection device, PAS, PDS, etc.), then in most cases this will lead to a denial of service on the part of the IED, leading to the fact that the latter will not capable of participating in information exchange. On the other hand, ISAS servers, equipped with high-performance 40 Gb/s communication interfaces, and the ISAS software architecture allow a significant number of Sampled Values ​​streams to be received through a single communication interface. Thus, in this project, the switches acted as a kind of diodes that passed traffic exclusively to the port to which the server was connected. Technically, this was achieved by setting a unique VLAN ID tag value for each outgoing Sampled Values ​​flow and including the corresponding switch ports in these VLANs, as well as including the switch port to which the server equipment was connected in all created VLANs. The only problem in implementing such a scheme was the monitoring and diagnostics of Sampled Values ​​streams. The volume of Sampled Values ​​traffic towards the server hardware was so large that it was absolutely impossible to control it using any software installed on a regular PC. The test rig we tried also failed - it simply lost Sampled Values ​​frames. To solve the problem of monitoring and diagnosing Sampled Values ​​streams, we again used the Tekvel Park complex, which copes with the task of simultaneous processing of up to 100 Sampled Values ​​streams. This allowed us to save time on physical reconnections to the LAN and on reconfiguring network equipment as part of commissioning.

Adjustment of relay protection and automation devices

Regulatory documents establish that “the adjustment of relay protection and automation devices is carried out by trained employees from among electrical personnel who have qualifications and experience. The work is carried out according to methods approved by the head of the enterprise. Testing equipment and measuring instruments used to carry out work must have test certificates and verification certificates.”

At a large enterprise, in the service of the chief power engineer, there are sections or groups of relay protection, automation and telemetering. If the enterprise does not have such a service, a specialized organization that has a licensed electrical laboratory on staff is engaged in setting up relay protection. Operating personnel must check the relay protection and automation according to the schedule, by visual inspection and reading information from the relay protection units. If signals about malfunctions, accidents or errors are received regularly, then checks and adjustments of relay protection should be carried out regularly; in the absence of such a possibility, third-party operational mobile teams of electrical laboratories are called.

The inspection results are recorded in the relay protection log and relay protection cards. They must reflect all work performed during the period that has passed since the last inspection, changes in settings, circuits, relay protection devices, newly introduced or taken out of service. Entries are also made in the operational log. All changes in the electrical circuit diagrams of the secondary switching cells are recorded. The absence of as-built documentation for relay protection devices and setting maps in the chief power engineer's service is a serious violation of the requirements of legislation and regulatory documents in the field of energy and entails punishment or large fines. During operation at the consumer's site, the personnel configures the relay protection in accordance with PTEEP: “the serviceability of emergency and warning alarms, switch position alarms, the presence of voltage on the operating current buses, all sources of direct and alternating current and the operating mode of recharging devices are checked.” Setting up relay protection also includes checking the insulation resistance of operating current circuits, the presence of operating current, the serviceability of fuses, the serviceability of ATS sources, the serviceability of switch control circuits, alarm circuits, and control of switching devices. It is also important to check “the correct position of circuit breakers, switches and other switching devices in the ATS circuit and the compliance of their positions with the primary circuit. Using the installed measuring instruments, they monitor the serviceability of the circuits of voltage transformers and fuses.”

Regulatory documents also provide a list of relay protection and automation faults that personnel can correct on their own. This:

  1. Turning on circuit breakers or replacing fuse links in VT circuits or power supply to relay protection devices.
  2. Disabling all relay protection and automation devices in the event of a break in the shutdown circuits of a switch or other switching device, followed by the dispatcher carrying out the measures provided for the connection, completely disconnected from the relay protection;
  3. Determination of the location of damage when a ground fault appears in the operational current circuits;
  4. Disabling devices that automatically close the circuit breaker in case of damage to the rectifiers supplying the circuits for turning on the electromagnetic drives.

Regulations

Regulatory documents, in accordance with the requirements of which relay protection is configured:

  • PUE 7th edition section 1, ch. 1.8 “Acceptance testing standards”
  • RD 34.45-51.300-97 “Scope and standards for testing electrical equipment”
  • Design documentation for equipment and relay protection units.
  • PTEEP
  • RD 34.35.302-90. “Standard instructions for organizing and performing work in relay protection devices and electrical automation of power plants and substations.”
  • RD 153-34.0-35.617-2001 “Rules for the maintenance of relay protection devices, electrical automation, remote control and signaling of power plants and substations 110-750 kV”
  • E.S. Musaelyan “Handbook for setting up EO ES and PS. Secondary circuit equipment"
  • Chernobrovov N.V. "Relay protection"
  • Kakuevitsky L.I. Krutitsky A.Yu. "Directory. Protection and automation relays"
  • Methods for checking relay protection and automation devices

ISAS System Configuration

As noted earlier, ISAS is almost completely configured using an SCD file, which is very convenient for engineers who know and understand the SCL language and data models according to the IEC 61850 standard. Each function implemented by ISAS is represented by a specific logical node and all interactions between functions ( including communications between functions within the same physical device) are described by InRef data objects of the logical nodes receiving the data. The main disadvantage of configuring ISAS was the lack of complete configuration software. At the same time, the ISAS SCL configuration files provide for the use of proprietary syntax, which prevented the use of third-party system configurators. Thus, the entire configuration was created manually (fortunately, we had an example of an already implemented project at our disposal, which we used as a template). Engineers who have ever tried to create or edit an SCD system configuration file can imagine the scale of the problem: the final SCD file for the project totaled more than 470,000 lines (see Figure 5).


Rice. 5. SCD configuration file for the ISAS system.

We believe that the configuration issues listed are temporary and will be resolved in the near future. At the very least, eliminating the proprietary syntax will allow the use of third-party system configurators, which will make the task of configuring the system as a whole easier. Another significant aspect related to working with configuration files is their management. Since the SCD file becomes the only configuration container for the entire substation, it requires special attention. In our case, we decided to manage the configuration file in a similar way to source files in programming, saving all versions and tracking the differences between them. We experienced all the advantages of this approach when the customer, after making configuration changes, deployed the system using an outdated SCD file (which was stored on a USB flash drive). This led to significant degradation of the system. To solve the problem of versioning SCD files, we used the Tekvel Park system of our own design. This system allows you to analyze an SCL file and present the differences between one version of the file and another. As noted earlier, the SCD file provides 99% of the ISAS system configuration. However, the remaining 1% is also very important and includes the assignment of server resources, which plays a significant role in ensuring the reliability of the system. The assignment of resources must be done in the most optimal manner, ensuring that the software runs without interruptions or time delays. In our case, we determined the assignment of virtual IEDs to processor cores manually. We are convinced that with serial implementation, resource assignment can be performed automatically, provided that data on the required resources is available for each logical node implemented within the IED.